Progress On Site...
Forge Design Studio has a number of projects currently under construction on site
Cedardore, West Wellow
Setting-out and the below ground sub-structure has been completed at Cedardore for Mayflower Homes. The concrete beam and block floor is in and the first lift of masonry is well underway. Progress should be good as the better weather arrives!!
Cowesfield Lodge
Site clearance and excavations have been dug and foundations poured at Cowesfield Lodge. The beam and block floor has been installed, and, as you can see, all the preparations have taken place ready for the mini-steel frame to arrive. Steel has been required to suit the light, open and airy extension. Almost 50sqm of new space is being created, as well the re-organisation of the existing house. This has been achieved under permitted development.Richard Stanton at RFS is the Main Contractor.
North Brook End Stud
The first phase of development is well underway at North Brook End Stud. The first floor staff apartment is being dry-lined, rooflights are in, the original exposed trusses have been cleaned. The contractors, Overton Builders, have got the first fix installations in place and are getting ready for the fit-out and all second fix joinery.